Construction Projects

2016 Construction Projects



Raymond Road Resurfacing


Contractor:

Aspro, Inc. of Waterloo, Iowa

Project Cost:

$266,944.02

Project Description:


Project limits were from Conard Road north to about 1,900’ south of Independence Ave.
The project included a 2.5” profile mill of the existing asphalt surfacing and then was resurfaced with a 2” intermediate lift of asphalt and a 2” surface lift of asphalt. Once paving was complete, the roadway was shouldered with 8’ wide granular shoulders and fresh rock was placed in driveways. New centerline and edge line pavement markings were also placed.
The project began on May 18, 2016 and was completed on June 1, 2016.

Kimball Ave. Resurfacing

  

Contractor:  

Aspro, Inc. of Waterloo, Iowa


Project Cost: 

$1,103,988.03


Project Description:  

Project limits are from the Eagle Road intersection north to the Waterloo City Limits. The project includes a 3” thick cold in place recycling of the existing asphalt surface.This will be followed by a 1.5” intermediate lift of asphalt and a 1.5” surface lift of asphalt. Once paving is complete, the roadway will be shouldered with 3’ wide granular shoulders and fresh rock will be placed in driveways. New rumble strips will be placed and new centerline and edge line pavement markings will also be placed.


The work started on Monday, June 13, 2016 and was completed on August 25th, 2016.

​Elk Run Road & Raymond Road Bridge Patching & Overlay

Contractor:

Wicks Construction, Inc. of Decorah, IA

Project Cost

: $280,002.55

Project Description:


Project if for repair of two bridges. One is located on Elk Run Road north of Dubuque Road the other is on Raymond Road over Crane Creek. The Elk Run Road bridge will be closed for patching and approach repairs. Elk Run Road will be detoured on Independence Ave. to Canfield Road to Dubuque Road. The Raymond Road bridge will consist of patching, an overlay and approach repairs. The detour for Raymond Road will be on Dunkerton Road to Hwy 281 to Cedar Wapsi Road. The project is expected to start in Early September.

Burton Ave Bridge Replacement 
Contractor: 

Ricklefs Excavating Ltd. of Anamosa, Iowa


Project Cost: 

$96,979.50


Project Description:  

The project is located 1/4 mile north of Dunkerton Road on Burton Ave. The project includes removing a 24-ft steel beam bridge with deteriorating timber piling and replacing it with a twin 10-ft x 6-ft reinforced concrete box culvert. The existing structure currently has load restrictions due to the deteriorated state of the piling; these will be removed once the project is completed.
The work was completed in October, 2016

Airline Highway Bridge Replacement 
Project Description: 

The project is located 1/4 mile east of Moline Road on Airline Highway, The project includes replacing an existing 60-ft steel beam bridge with deteriorating timber piling with a 40-ft Composite Beam-in-Slab bridge constructed by the secondary roads maintenance crews. 

Marquis Road Bridge Replacement 
Project Description: 

The project is located 1/2 mile east of Elk Run Road on Marquis Road, The project includes replacing an existing 22-ft timber bridge with a 35-ft Composite Beam-in-Slab bridge constructed by the secondary roads maintenance crews.